消火栓(箱安裝基本要求:
Basic requirements for the installation of fire hydrants (boxes):
消火栓栓口離地高度1.1m,,栓口朝外。
The height of the fire hydrant mouth from the ground is 1.1m, with the mouth facing outward.
單個(gè)消火栓不應(yīng)安裝在消防箱門軸側(cè),。
A single fire hydrant should not be installed on the side of the fire box door shaft.
消防箱箱體安裝垂直度允許偏差3mm,,安裝完畢封閉多余孔洞及孔洞縫隙。
The verticality of the installation of the fire box body is allowed to deviate by 3mm. After installation, excess holes and gaps in the holes should be closed.
消火栓箱門易打開,,開啟角度不小于120°,;采用石材等裝飾材料的消防箱門應(yīng)開啟靈活(開啟拉力≯50N;箱門外標(biāo)識(shí)明顯,。
The fire hydrant box door is easy to open, with an opening angle of no less than 120 °; Fire box doors made of decorative materials such as stone should be opened flexibly (with an opening force of not more than 50N; the markings on the outside of the box should be clear.
消火栓箱內(nèi)水龍帶、水槍,、軟管等安放到位,。
The water hose, water gun, and hose inside the fire hydrant box are placed in place.
消火栓(箱安裝注意事項(xiàng):
Fire hydrant (box installation precautions:
消火栓支管以栓閥的坐標(biāo)、標(biāo)高定位甩口,,核定后穩(wěn)固消火栓箱,,待箱體找正固定后再安裝栓閥。消火栓箱安裝的垂直度允許偏差為3mm,。
The fire hydrant branch pipe is positioned with the coordinates and elevation of the hydrant valve, and after verification, the fire hydrant box is stabilized. After the box is aligned and fixed, the hydrant valve is installed. The allowable deviation for the verticality of the installation of the fire hydrant box is 3mm.
消火栓箱體若采用暗裝或半暗裝時(shí),,需在土建砌磚墻時(shí),預(yù)留好消火栓箱洞,,待消火栓箱就位找正找平后,,用水泥砂漿填塞箱四周空間;明裝時(shí)采用膨脹螺栓固定,。安裝在輕質(zhì)隔墻上應(yīng)有加固措施,。
If the fire hydrant box is installed in a concealed or semi concealed manner, it is necessary to reserve the fire hydrant box hole when building brick walls in civil engineering. After the fire hydrant box is in place, align and level it, fill the space around the box with cement mortar; Expansion bolts are used for fixation during open installation. Reinforcement measures should be taken when installing on lightweight partition walls.
箱體配件安裝時(shí),消防水龍帶應(yīng)折好放在掛架上卷實(shí),、盤緊,;消防水槍豎放在箱體內(nèi)側(cè),自救式水槍和軟管放在掛卡上或放在箱底部,。消防水龍帶與水槍,、快速接頭的連接,一般采用16#銅絲綁扎兩道,,每道不少于兩圈,;使用卡箍時(shí),在里側(cè)加一道銅絲,。
When installing the accessories of the box, the fire hose should be folded and placed on the hanger, rolled tightly and coiled tightly; The fire water gun is placed vertically on the inside of the box, and the self rescue water gun and hose are placed on the hanging card or at the bottom of the box. The connection between the fire hose, water gun, and quick connector is generally tied with 16 # copper wire in two layers, each with no less than two turns; When using clamps, add a copper wire on the inner side.